Battery selection for industrial backup & UPS

Start with the UPS model, backed-up load, required outage runtime and recovery time. Check the proposed battery against DC cutoff, charger and rack constraints.

Prepare a project brief

What to specify

Project requirements
DecisionInputs to recordHow to check
Load and durationBacked-up AC kW or battery-side DC kW/A, required minutes and repeat outage profile.Check battery terminal voltage and available energy at the actual discharge power and cutoff.
Recharge windowUPS charger voltage range, available DC current and time until the next required backup event.Check recovery under representative conditions including temperature derating and concurrent load.
IntegrationBMS interfaces, protection coordination, rack envelope, ventilation and service access.Confirm disconnect behavior and acceptance checks on the installed system.

Download project worksheet (CSV)

Cell references for initial screening

Use these source values for an initial comparison. Pack voltage, current capability, physical fit and test evidence depend on the proposed build.

Dated cell references
ModelCell routeNominal cell valuesSource edition
LFP50LFP · Prismatic3.2 V / 50 Ah2026
LTO40LTO · Cylindrical2.3 V / 40 Ah2026

Sample acceptance

Record runtime, terminal voltage and temperature at agreed load and ambient conditions. Confirm recovery after a representative outage. Review evidence for the exact rack or pack before procurement.

IEC 62619:2022 scope for industrial secondary lithium batteries · Review the evidence checklist